Six simple steps to a smooth and timely provisioning journey


Six simple steps to a smooth and timely provisioning journey

When you’ve worked hard to win valuable new business and get to placing your order with us, the last thing you want is any nasty delays that prevent you getting your customer up and running - especially for things that can easily be avoided!

15 July 2019

Nicholas Paxon, Senior Provisioning Coordinator

When you’ve worked hard to win valuable new business and get to placing your order with us, the last thing you want is any nasty delays that prevent you getting your customer up and running - especially for things that can easily be avoided!

One of the main factors that will influence how quickly your order will progress lies right at the start of process with the Customer Requirements Form (CRF).

Providing detailed and accurate information on your CRF means the order can be signed and validated and the provisioning journey can proceed smoothly - so to help you we’ve come up with six simple tips for CRF completion:

1. Address accuracy

Misspelling a street name or not including the building or unit number can delay your order. The easiest way to avoid this is to check that your details match up to Royal Mail’s details: https://www.royalmail.com/find-a-postcode

2. Room and floor accuracy

If you’ve put ‘n/a’ in the room section of the CRF there is no guarantee that an engineer will know where in a building the required works need to be carried out - a simple description of where the room is and which floor it's on if it’s in a multi storey building will help to avoid any unnecessary delays.

3. Asbestos registers

It’s important that you’re accurate when telling us the age of the building where the works will be carried out. If the property was built pre 2000 then you will need to include a copy of the asbestos register with the CRF. Failure to supply one when required will lead to painful cancellation charges as well as delays to the order.

4. Site contact details

To ensure engineer visits are completed in a smooth and timely manner, we need to have contact details for someone who will be available at the site at the time of the appointment. In some cases partners have put their own contact details in here and it’s meant the engineer can’t get into the building because they aren’t physically on site.

5. Building manager / route approver

This isn’t a specific field in the CRF but getting this information to us in the notes early doors enables the engineer to speak to the right person and more accurately plan the works required to make the customer appointment much more efficient.

6. Landlord contact details

Again not a required field in the CRF, but including these details in the notes means that in cases where wayleave is required it can negate the lead times required to complete this process.

How we’re working to make your provisioning journey easier

In addition to these six simple tips you can follow, we’re also continuously improving our provisioning processes to make it even easier for you. We’ll keep you updated on all of the latest developments and if you have any suggestions for how we can further improve our provisioning process then please do contact us and let us know.